AIRPORT IMPROVEMENT PROJECTS
To accommodate the City of Galveston, Galveston County, and aviation's' continued growth, Scholes International Airport uses its Capital Improvement Program as the primary planning tool for identifying and prioritizing airport development.
Airfield Pavement Rehabilitation
Start Date
December 10, 2018
Est. End Date
October 2019
Prime Contractor
RAC Industries, LLC
Michael Price, Project Superintendent
On Site RPR
JDT RPR Services
Harry Smart, Resident Project Representative
Project Cost
$5,180,000
Funding Source - 90/10 Grant
TxDOT Aviation paying 90% or $4,662,000
TIRZ 14 paying 10% or $518,000
Other Ongoing Projects: Airport Hangar Project, Control Tower Rehab.