Here's the latest on the construction project happening at the airport. All information below is subject to change due to weather conditions and equipment breakdowns.

Runway 14/32 Closure - Blue Construction Zone as outlined in Blue:

Runway 14/32 and Taxiway B at the approach end of Runway 32 will be closed beginning Monday, October 14th through Monday, November 4, 2019. During this time, the approach lighting system (ALS) and ILS approach to Runway 14 will be out of service, and the lights to the runway will be turned off.

Work will be done on concrete sections of both runway ends. While the runway is closed, RAC will also finish the south end of Taxiway B, located near the approach end of 32.

Barricade locations:

  1. Taxiway A, east of the approach end of 36

  2. Taxiway B, south of the South Ramp area

  3. Taxiway D, west of Runway 18/36

  4. Taxiway E, west of the approach end of Runway 18

  5. Runway 14/32 on both sides of Runway 18/36

Remaining Work to be done:

1. Once the work on Runway 14/32 is completed, the runway intersection must be done. We plan to do this work at night, between 10:00pm and 5:00am. Work is scheduled to last 10 days.

2. Crack sealing needs to be completed on Taxiway D between the Ramp and Runway 18/36.

3. Striping has been delayed, but the North Apron, Taxiways E

and D, and Runway 14/32 remains to be striped.