Runway 14/32 (completed)
top of page
Flying Planes
RSS Feed

Runway 14/32 (completed)

All information below is subject to change due to weather conditions, contractor availability, and equipment breakdowns.


Scholes Airport Runway 14/32 Aerial

North Apron:

Work on the North Apron consists of two projects that could take up to two months to complete the job.

  • Project 1 is to rehabilitate the concrete areas not included in our last pavement rehab project. The concrete work on the apron should finish up by Friday, June 4th (NOTAM 05/015). Please use caution near the barricaded areas. Be aware of moving vehicles and workers transitioning to the worksite.

  • Project 2 is to remove and replace all of the old joint seals on the North Apron. This work is currently not scheduled.

Runway 14/32:

Work to be done is to rehabilitate the asphalt sections of Runway 14/32 and restripe the runway. This runway closure does not affect the intersection since no work is being done at the intersection. The runway work will start on June 2nd. We expect this work to last until the end of June.


Today we have issued the following NOTAMs:

  1. NOTAM 06/001 – Runway 14/32 closed starting June 2nd at 9:00 am (1400 UTC) to June 30th at 5:00 pm (2200 UTC).

  2. NOTAM 06/002 – Taxiway D closed west of Runway 18/36 starting June 2nd at 9:00 am (1400 UTC) to June 30th at 5:00 pm (2200 UTC).

  3. NOTAM 06/003 – Taxiway E closed west of Runway 18/36 starting June 2nd at 9:00 am (1400 UTC) to June 30th at 5:00 pm (2200 UTC).

If you have any questions please contact Mike Shahan, Airport Director, at 409-797-3593 or email mshahan@galvestontx.gov.