Runway 18-36 Rehabilitation Updates (Completed)

Please see below for our most up to date information on Runway 18-36 Rehab. The newest update will always be at the top for your convenience.



PROJECT COMPLETE BOTH RUNWAYS FULLY OPERATIONAL



 


STARTING OCTOBER 24, 2022, BOTH RUNWAYS WILL BE CLOSED NIGHTLY AT 9:00 PM AND REOPENING AT 6:00 AM EVERY MORNING.


October 21, 2022


Update #7


Good afternoon everyone,


This update is our seventh update for our Runway 18/36 rehabilitation project. As with previous projects, new information is in RED font, and we will update you on the progress of the project and changes that limit your access to the runways and taxiways.


Due to weather conditions, contractor availability, and equipment breakdowns, all information below is subject to change.


Runway 18/36:

The runway work comprises five phases that will take 120 calendar days to complete the repairs. Please see the enclosed attachment for each Phase location.


Current Work Areas:

· Phase 1: starts at the approach end of Runway 36 and Taxiway A and goes north to the south side of the runway intersections. Spall repairs are done, and joint seal repairs are ongoing.


· Phase 2: is at the runway intersection and includes all concrete for both runways and Taxiway C to the hold short line. Work final work starts in this area the night of October 24. Runway 14/32 will be closed each night at 9:00 PM and opened each morning at 6:00 AM to complete joint seal repairs at the runway intersection and mark and stripe the runway intersection.


· Phase 3: includes work north of Taxiway C and south of Taxiway E. The spall and joint seal repairs are complete.


· Phase 4: includes spall repair and joint seal work between the hold short lines on Taxiway E and Runway 18. The spall and joint seal repairs are complete.


· Phase 5: includes marking and striping Runway 18/36 and taxiways A, C, D, and E up to and including the hold short markings. The striping work will start the week on October 24 through November 4 and will be done during the day, except for the work at the runway intersection.


CURRENT NOTAMS:

· GLS 10/008: RWY 18/36 CLSD through November 10, 2022, at 5:00 PM (2200Z)

· GLS 10/009: TWY A CLSD through November 10, 2022, at 5:00 PM (2200Z)

· GLS 10/012 RWY 14/32 CLSD DAILY between 9:00 PM (0200Z) and 6:00 AM (1100Z) from October 24 through November 4, 2022.


Thank you,


Mike Shahan, Airport Director




Tenant Update - 7
.pdf
Download PDF • 334KB

NOTAM Info
.pdf
Download PDF • 231KB

 


October 7, 2022


Update #6


Good afternoon everyone,


This update is our sixth update for our Runway 18/36 rehabilitation project. As with previous projects, new information is in RED font, and we will update you on the progress of the project and changes that limit your access to the runways and taxiways.


Due to weather conditions, contractor availability, and equipment breakdowns, all information below is subject to change.


Runway 18/36:

The runway work comprises five phases that will take 120 calendar days to complete the repairs. Please see the enclosed attachment for each Phase location.


Current Work Areas:

· Phase 1: starts at the approach end of Runway 36 and Taxiway A and goes north to the south side of the runway intersections. Spall repairs are done, and joint seal repairs are ongoing.


· Phase 2: is at the runway intersection and includes all concrete for both runways and Taxiway C to the hold short line. This project phase is done, except for some joint seal repairs and stripping.


· Phase 3: includes work north of Taxiway C and south of Taxiway E. The spall repairs and joint seal work is complete between Taxiway C and D and continues north of Taxiway D to the south of Taxiway E.


· Phase 4: includes spall repair and joint seal work between the hold short lines on Taxiway E and Runway 18. Phase 4 is complete except for stripping, and Taxiway E will be open by 6:00 PM today.


· Phase 5: includes marking and stripping Runway 18/36 and all taxiways up to and including the hold short markings. This work should begin the week of October 24 and will require Runway 14/32 to be closed every night for approximately two weeks between 9:00 PM and 6:00 AM. A new NOTAM will be issued 72 hours before the nightly closure starts.


CURRENT NOTAMS:

· GLS 10/008: RWY 18/36 CLSD through November 10, 2022, at 5:00 PM (2200Z)

· GLS 10/009: TWY A CLSD through November 10, 2022, at 5:00 PM (2200Z)


Thank you,


Mike Shahan

Airport Director




Tenant Update - 6
.pdf
Download PDF • 1.05MB

NOTAM Info
.pdf
Download PDF • 269KB


 


Update #5


September 22, 2022


Good afternoon everyone,


This is our fifth update for our Runway 18/36 rehabilitation project. As with previous projects, new information is in RED font, and we will update you on the progress of the project and changes that limit your access to the runways and taxiways.


Due to weather conditions, contractor availability, and equipment breakdowns, all information below is subject to change.


Runway 18/36:

The runway work comprises five phases that will take 120 calendar days to complete the repairs. Please see the enclosed attachment for each Phase location.


Current Work Areas:

· Phase 1: starts at the approach end of Runway 36 and Taxiway A and goes north to the south side of the runway intersections. Spall repairs are done, and joint seal repairs and stripping are pending.


· Phase 2: is at the runway intersection and includes all concrete for both runways and Taxiway C to the hold short line. This phase of the project is done, except for stripping.


· Phase 3: includes work north of Taxiway C and south of Taxiway E. The spall repairs and joint seal work is complete between Taxiway C and D, and Taxiway D will be open starting September 24 at 6:00 AM. Work continues north of Taxiway D to Taxiway E. Stripping will be completed during Phase 5, which is the last phase of the project.


· Phase 4: includes spall repair and joint seal work between the hold short lines on Taxiway E and Runway 18. Taxiway E will be closed during this project phase.


· Phase 5: includes marking and stripping Runway 18/36 and all taxiways up to and including the hold short markings.


CURRENT NOTAMS:

  • GLS 06/014: RWY 18/36 CLSD between June 11, 2022, at 6:00 AM (1100Z) to October 19, 2022, at 5:00 PM (2200Z)

  • GLS 07/015: TWY A CLSD through October 19, 2022, at 5:00 PM (2200Z)

  • GLS 09/026: TWY E CLSD starting Saturday, September 24, 2022, at 6:00 AM (1100Z) through October 19, 2022, at 5:00 PM (2200Z)

GLS 09/027: Taxiway D CLSD through September 24, 2022, at 6:00 AM (1100Z)