RSS Feed
  • dtitus191

South Apron and South Ramp Rehabilitation Project

Please see below for our most up to date information on South Apron and South Ramp Rehab. The newest update will always be at the top for your convenience.

 

Update #1


November 21, 2022


Good afternoon everyone,


I wanted to let everyone know that our upcoming TxDOT rehabilitation project on the South Apron and South Ramp started today. Ambrozi Contracting will replace joint seals, some concrete slabs, spall repairs, and drainage improvements. As with previous projects, we will send updates with any changes or work that might limit your access to your hangar.


All information below is subject to change due to weather conditions, contractor sequencing, and equipment breakdowns.


South Apron and South Ramp:

The apron and ramp work comprises eight phases that will take 150 calendar days to complete the work. Please see the enclosed attachment for each Phase location.


  • Phase 1: This phase should take 30 calendar days to complete.

  1. South Apron work starts west of the PHI apron and east of the non-movement line (outlined in Red) in the attached drawing.

  2. South Ramp work included most of the South Ramp, except for the area where some hangars were before Hurricane Ike.

  • Phase 2: This phase is west of the PHI apron and east of the non-movement line (outlined in dark Yellow) in the attached drawing. This phase should take 15 calendar days to complete.

  • Phase 3: This phase (outlined in Green) is north and west of the PHI apron and east of the non-movement line in the attached drawing. This phase should take 15 calendar days to complete.

  • Phase 4: This phase (outlined in dark Green) is in front of the east ERA hangar and extends towards Phase 1. This phase should take 15 calendar days to complete.

  • Phase 5: This phase (outlined in Aqua/Cyan) is in front of the west ERA hangar and Hangar 73 and goes west to Taxiway B. This phase should take 15 calendar days to complete.

  • Phase 6: This phase (outlined in Blue) is west of Phase 5, goes to the west end of the apron, and necessitates closing Taxiway B. This phase should take 15 calendar days to complete.

  • Phase 7: This phase (outlined in Magenta) is west of Phases 1, 2, and 3, goes to the west end of the apron, and closes the Parallel Taxiway. This phase should take 25 calendar days to complete.

  • Phase 8: This phase is marking and striping the Apron and South Ramp. This phase should take 20 calendar days to complete. Once done, the project is over.


NOTAMS will be issued on 11/22/22 for men and equipment working on the South Apron and South Ramp. Please use caution when in this area.


Please let me know if you have any questions or concerns about this update.


Sincerely,

Mike Shahan



Tenant Update - 1 dated 11-21-22
.pdf
Download PDF • 1.27MB